ACC was the civil and structural steel contractor for Doosan Heavy
Industries for the Umm Al Nar desalination plant, which was completed
in 2001.
The plant is able to produce 62.5 MIGD and was built on a fast
track basis: out of a total of 65,000 cubic metres of concrete,
50,000 cubic metres were poured in less than five months. Output
is achieved through five evaporators (12.5 MIGD each) with five
attendant boilers.
The project consisted of five distillers (each 90 metes long, 30
metes wide and weighs 3,500 tons), five low pressure boilers, four
water tanks (each 75 metres in diameter), a one kilometre discharge
culvert, an outlet structure, five kilometre roadworks, a remineralization
plant, a potable water pump station and other balance of plant structures
(31 structures in total).
|